Challenge of the project

To fulfil the needs of its new manufacturing site near Dunkirk, ArcelorMittal wants to increase the power of its high voltage substation. MasterGrid is consulted to make the engineering studies and execute extension works on the 225 kV substation.

Our response

During a year of work, our different teams mobilized to realize this extension of 4 000m² of the 225 KV substation which includes 2 busbars, 2 bays with each: 2 disconnectors, 1 circuit breaker, 1 bus coupler and 1 transformer 225/20kV 55MVA, 1 20kV underground cable, 1 20kV Busbar, as well as a complete system of line, cable and transformer protection.

A major mobilization of our know-how, from project conception through to completion.

Check

Coordination by a single team

Check

Asset performance increased

Check

Adaptation works made easy and manufacturer know-how

Forme Join